Aas-Jakobsen is the lead consultant and client’s contractual party. Sub-consultants from the network will be used for disciplines other than civil and construction engineering and engineering management.
The E16 Sandvika to Wøyen section is made up of the following main elements:
The Bjørnegård Tunnel will be constructed as a twin bore tunnel, 9.5 cross-section, with a length of around 2.3 kilometres. Of this, around 500 metres will be a concrete tunnel, some of which will be built in extremely deep construction pits, braced with secant pile walls and special sheet pile walls made of pipe piles. The connection zones in the south to the existing Kjørbo tunnels will be excavated using retaining walls and special drilling methods.
The open-air section of E16 between Bærumsveien and the section boundary at Vøyenenga. The section is around 1.4 kilometres long. This short section contains two complete stack interchanges over the E16, the Bærumsvei interchange and Lommedals interchange. The section contains 7 small bridges/pedestrian and cycleway bridges and 8 large road bridges. Because of particularly poor ground conditions, it has proved necessary to add in 4 lightweight embankments, around 18,000 m2 of piled concrete slab and around 3500 m2 of ground reinforcement with piles and pile caps for the ground under the road superstructure.
From the Sandvik River and around 0.8 kilometres uphill along Bærumsveien, Dælibekken stream will be reopened.
The existing E16 corridor will be demolished, including 5 road bridges. Brynsveien will be rebuilt with a new bridge over the Sandvik River, and a new Industriveien with intersections will be built. The current E16 between Brynsveien and Franzefoss will be modified to become a local road and bypass road in the event of tunnel closures. A new heavy vehicle checkpoint will be built at Økri, to replace the old checkpoint at Løxa.
As of autumn 2017, the status is that the construction work on both construction contracts is proceeding at full speed. The tender documentation for the local road system in Sandvika and up to Franzefoss still has to be prepared. Construction work on this contract is expected to start in spring 2019 at the earliest, with completion in the late autumn of 2020. There is still expected to be a good deal of supervisory work and assistance to the client until the permanent four-lane E16 is opened to traffic, which is scheduled to be in the autumn of 2019.
Lars Narvestad
Direktør Samferdsel
lna@aaj.no
+47 932 23 060
To provide the best experiences, we use technologies such as cookies to store and/or access information on your device. Consenting to these technologies will allow us to process data like browsing behavior or unique IDs on this site. Not consenting or withdrawing consent may negatively affect certain features and functionalities.